Name of the Job Site / Project:
Hunter Road Industrial
Project Location (Address or General Area):
5032 Mason Road, Atlanta, GA
What is being built at this location?
An 88,302 SF industrial warehouse.
What is Carmichael Development’s role in the project?
Carmichael Development is handling the sitework, including erosion control, grading (approximately 55,000 CY of earthwork), and the installation of underground utilities such as storm drainage, sewer, and domestic water systems. Approximately 5,000 LF of pipe will be installed.
Who is the General Contractor (GC) or primary client on this project?
Duffey Southeast
What is the current phase of construction?
The project is currently in the mass grading phase, with earthwork nearly complete. The team is preparing to begin storm and sewer utility installation within the next few weeks.
Are there any notable challenges or highlights of this project?
The project has experienced typical sitework challenges, requiring flexibility with changing field conditions while maintaining a strong focus on safety and daily production goals. Despite these factors, progress has remained on track, with most of the mass grading completed and storm and sewer installation scheduled to begin soon.
A key highlight of this project has been the production rate, with approximately 5,500 cubic yards of material being moved per day. This efficiency has allowed the team to get ahead of schedule and turn over the building pad to the GC much sooner than originally anticipated.